July 24, 2010

To: Earl Wiklund, Director

From: Golf Course Maintenance Jim Ferrin, Superintendent

Subject: Golf Course Maintenance Update

Overview of the Week

Updates and Pending Issues.

Work Completed Timber Creek

·        Golf course mowed and detailed

·        Greens treated for fairy ring

·        Fairways and roughs fertilized

·        Potassium applied to greens and tees

Work Completed Sierra Pines

·        Golf course mowed and detailed

·        Greens treated for fairy ring

·        Fairways and roughs fertilized

·        Potassium applied to tees and greens

Driving Range

Work Scheduled for the Week of July 26, 2010

 

Work Completed Landscape

Work Scheduled for the Week of July 26, 2010