January 28, 2012

To: Earl Wiklund, Executive Director

From: Golf Course Maintenance -Jim Ferrin, Golf Course Superintendent

Subject: Golf Course Maintenance and Landscape Update

 

Overview

Updates and Pending Issues

Work Completed Timber Creek

·        Golf course greens and fairways fertilized lightly

·        Detail work: edging cart paths and sprinkler heads

·        Mowing where needed

Work Completed Sierra Pines

·        Golf course greens and fairways fertilized lightly

·        Detail work: sprinkler heads and cart paths edged

·        Mowing where needed

Driving Range

Work Schedule for week of January 30, 2012

Work Completed Landscape

Work Scheduled for the Week of January 30, 2012